Barretto Bypass Road 2024-06-14

This is my 3rd Segment!

It is being worked on. Highlights are, the two main culverts are finished and the road work has been lengthened about 100 meters. Judging by the direction of the lengthening, the road seems to aim in the direction of the Rizal Ext. in Barrio Barretto. Keep in mind the present project only deals with a 800 meters section only.

 

The previous two Facebook Presentations are located here:

 

Facebook posting 2023-06-05, First Presentation, Click here:

 

Facebook, album and posting URLs 2023-11-22, Second Presentation, Click here:

 

————————————————————-

240614 Bo.Barretto Bypass Rd. Picture #01 shows the concrete box culvert and the first ridge.

————————————————–

Pictures # 02 & 03 are Google Earth graphs to show the location and landmarks of the Barrio Barretto Bypass Road Project.

240614 Bo.Barretto Bypass Rd. Picture # 02.

240614 Bo.Barretto Bypass Rd. Picture # 03.

——————————————-

Pictures # 04 to # 07 show the First Ridge from different angles and distances. We see dump truck activities and a backhoe in action. One dump truck became a casualty. I think, the project is to widen the cut thru the ridge.

240614 Bo.Barretto Bypass Rd. Picture # 04.

240614 Bo.Barretto Bypass Rd. Picture # 05.

240614 Bo.Barretto Bypass Rd. Picture # 06.

240614 Bo.Barretto Bypass Rd. Picture # 07.

———————————————-

Pictures # 08 to # 10 show the Second Ridge as I approach. We see dump truck activities and a backhoe in action. I think, the project is to widen the cut thru the ridge.

240614 Bo.Barretto Bypass Rd. Picture # 08.

240614 Bo.Barretto Bypass Rd. Picture # 09.

240614 Bo.Barretto Bypass Rd. Picture # 10.

———————————————

Pictures # 11 & # 12 is a view of the end of this project in the direction of Rizal Ext. Road in Barrio Barretto.

240614 Bo.Barretto Bypass Rd. Picture # 11.

240614 Bo.Barretto Bypass Rd. Picture # 12.

———————————————————–

240614 Bo.Barretto Bypass Rd. Picture # 13 show that there are some people that live left and right of the bypass road project.

——————————————————-

240614 Bo.Barretto Bypass Rd. Picture # 14 is a view back to the Second Ridge from on top of the synthetic material pipes culvert.

———————————————————-

Pictures # 15 to # 18 are views of the about 100 meter lengthening of the Barretto Bypass Road.

240614 Bo.Barretto Bypass Rd. Picture # 15.

240614 Bo.Barretto Bypass Rd. Picture # 16.

240614 Bo.Barretto Bypass Rd. Picture # 17.

240614 Bo.Barretto Bypass Rd. Picture # 18.

————————————————————

240614 Bo.Barretto Bypass Rd. Picture #19 is a view back from the present and new end of this bypass project towards the Second Ridge across the synthetic material pipes culvert.

————————————————————————–

240614 Bo.Barretto Bypass Rd. Picture # 20 is scenery shot from the present and new end of this bypass project towards the gorge to Subic Town Barrio Mangahan. The view is across the Matain River Valley, the Naugsol village and valley.

Leave a Reply

Your email address will not be published.